1. Build Footings with Dimensional Lumber according to all Local and National Building Codes.
|
|
| 2. Place Rebar According to Structural Details and building codes.
|
|
3. Pour Concrete
|
|
| 4. Strip Footings
|
|
5. Chalk lines and Set Bottom Cleats. |
|
| 6. Set Outside wall panels.
|
|
7. Install Steel according to Structural Details and building codes. |
|
| 8. Set Inside wall panels and top Cleats.
|
|
9. Brace As Necessary. |
|
| 10. Pour Walls with Hold-Downs Placed According to Details.
|
|
11. Strip and Clean Panels The Next Day.
|
|
|
|